An email from Steve Smith (SigNet Technologies) outlining a plan to upgrade recording hardware and racks at a facility. The plan involves 'Com Techs' installing new equipment while maintaining the old system to ensure continuous recording, with a colleague named Jeff McKenzie scheduled to visit the site.

People (3)

Name Role Context
Steve Smith Federal Sales Representative
Sender of the email; works for SigNet Technologies / Convergint Federal Solutions.
Jeff McKenzie Employee
From SigNet; scheduled to be on site Monday; sending NCIC forms.
Com Techs Technicians
Currently un-boxing new hardware and setting up racks.

Organizations (2)

Name Type Context
SigNet Technologies
Company employing Steve Smith and Jeff McKenzie; providing security/recording systems.
Convergint Federal Solutions
Partner organization or parent company listed in signature.

Timeline (2 events)

Monday (Specific date unknown)
Jeff McKenzie from SigNet scheduled to be on site.
On-site
Unknown
Hardware installation and system cutover process.
On-site

Locations (2)

Location Context
Address for SigNet Technologies / Convergint Federal Solutions.
Unspecified location where hardware is being installed (likely a correctional facility given the context of NCIC form...

Relationships (1)

Steve Smith Colleagues Jeff McKenzie
Both associated with SigNet Technologies in the email.

Key Quotes (3)

"First priority is to restore recording to all channels."
Source
EFTA00036121.pdf
Quote #1
"The old system will run continuing to record the existing remaining channels until the new system is ready for cutover."
Source
EFTA00036121.pdf
Quote #2
"Jeff McKenzie from SigNet will be on site Monday. He will be sending NCIC forms."
Source
EFTA00036121.pdf
Quote #3

Full Extracted Text

Complete text extracted from the document (1,469 characters)

[REDACTED]:
Here is the game plan:
The Com Tech’s are currently un-boxing the new hardware and getting the equipment in the new racks. Need power and network drops and IP Addresses to the new racks. Need to make sure the existing coax jumpers from the old recorders will reach the new racks for cutover between old equipment and new.
Jeff McKenzie from SigNet will be on site Monday. He will be sending NCIC forms.
The old system will run continuing to record the existing remaining channels until the new system is ready for cutover. First priority is to restore recording to all channels. Redundancy/PTZ control etc. will be converted once recording is restored.
The existing analog matrix switch will remain for PTZ control and PLC camera call up.
I will provide an update once we are on-site and assess current site conditions.
Steve Smith | Federal Sales Representative
SigNet Technologies | Convergint Federal Solutions
12300 Kiln Ct Suite E, Beltsville, MD 20705
Office [REDACTED] | Mobile: [REDACTED] | Direct:
[REDACTED]
This e-mail and any attachments to it are intended only for the identified recipients. It may contain proprietary or otherwise legally protected information of SigNet Technologies, Inc. Any unauthorized use or disclosure of this communication is strictly prohibited. If you have received this communication in error, please notify the sender and delete or otherwise destroy the e-mail and all attachments immediately.
EFTA00036121

Discussion 0

Sign in to join the discussion

No comments yet

Be the first to share your thoughts on this epstein document