This document is a presentation slide detailing a financial cost estimate for the construction of a '10 mgd Floridan Plant' (likely a water treatment facility sourcing from the Floridan Aquifer). It lists specific infrastructure costs such as 'Membrane Building w/LPRO system' ($19M) and 'Raw Water Wells & Piping' ($13.5M), culminating in a total conceptual cost of $80,250,000. The document contains a Bates stamp indicating it is part of a House Oversight Committee investigation record.

Organizations (1)

Name Type Context
House Oversight Committee
Document bears Bates stamp HOUSE_OVERSIGHT_016661

Locations (1)

Location Context
Water source for the proposed plant

Key Quotes (1)

"Assumes no additional cost for land."
Source
HOUSE_OVERSIGHT_016661.jpg
Quote #1

Full Extracted Text

Complete text extracted from the document (826 characters)

FLORIDAN AQUIFER PLANT COSTS
Cost Estimate for 10 mgd Floridan Plant
Site Work & Site Electrical $ 3,000,000
Raw Water Wells & Piping $ 13,500,000
Pretreatment System $ 5,000,000
Membrane Building w/LPRO system $ 19,000,000
Chemical Feed Systems $ 2,000,000
Yard Piping $ 1,500,000
Clearwell $ 1,200,000
Transfer Pump Station $ 1,000,000
High Service Pump Station $ 2,100,000
Ground Storage Tanks $ 3,900,000
Brine Disposal Injection Well $ 6,000,000
Dedicated Water Transmission Piping $ 6,000,000
Conceptual Cost $ 64,200,000
General Requirements (2%) $ 1,284,000
Construction Mark-up (3%) $ 1,926,000
Mobilization (2%) $ 1,284,000
Contingency (10%) $ 6,420,000
Engineering and Other Non-Construction Costs (8%) $ 5,136,000
TOTAL CONCEPTUAL COST $ 80,250,000
Assumes no additional cost for land.