Type: Timeline diagram
File Size: 1.09 MB
Summary

This document outlines a 6 to 9 month, 150-day permitting process for a development agreement in Clark County. The timeline details key steps for an investor, including submitting a traffic study and RISE reports, a pre-submittal conference, agency reviews, and negotiations, culminating in a development agreement hearing. The process begins after securing initial permit approvals from the Paradise Town Advisory Board.

People (3)

Name Role Context
investor
developer
applicant

Organizations (2)

Timeline (2 events)

Pre-submittal conference
Development agreement hearing

Locations (2)

Location Context

Relationships (2)

developer/investor/applicant seeks a development agreement through a permitting process Clark County
developer acquires permit approvals from before starting the county process Paradise Town Advisory Board

Full Extracted Text

Complete text extracted from the document (1,344 characters)

6 to 9 Month Permitting Process to Break Ground
The following is an outline of the estimated 6 to 9 month permitting process an investor will follow to enter into a development agreement within Clark County. Prior to starting the development agreement process with the County, the developer would acquire permit approvals from the Paradise Town Advisory Board.
[Timeline]
Top Row:
Traffic study submitted
RISE reports distributed upon receipt
Pre-submittal conference
Redistribute RISE reports response from agencies
RISE acceptance letter
Development agreement hearing
Day Markers:
Day 1
Day 15
Day 30
Day 45
Day 60*
Day 105*
Day 150
Bottom Row:
Pre-submittal filing: initial regional infrastructure services evaluation ("RISE") reports submitted. evidence of traffic study submittal.
Agencies encouraged to submit draft comments
Agencies encouraged to submit draft comments
Revised RISE reports submitted by applicant
Special use permit filed
Commence and continue to negotiate Development agreement**
[Footnotes]
*Acceptance letter may be issued within 30 days of presubmittal conference depending upon applicant's response.
**Development Agreement may be submitted in conjunction with Special Use Permit if negotiations are complete.
Fixed timeline mav be flexible dependent upon applicant's response time.