This document is a presentation slide or financial exhibit detailing the estimated costs for a 10 mgd (million gallons per day) desalination plant. It itemizes construction costs totaling $128.4 million and adds percentage-based soft costs (contingency, engineering, etc.) for a total conceptual cost of $160.5 million. The document bears a 'HOUSE_OVERSIGHT' Bates stamp, indicating it is part of a congressional investigation.
| Name | Type | Context |
|---|---|---|
| House Oversight Committee |
Source of the document via Bates stamp HOUSE_OVERSIGHT
|
|
| City |
Mentioned in footer: 'Assumes plant on City property'
|
| Location | Context |
|---|---|
|
Proposed location for the desalination plant
|
Complete text extracted from the document (1,044 characters)